Use the permit lookup · Compare towns
Do You Need a Permit in Monona?
Yes permit neededNo no permitDepends depends on the workAsk not published, call the office
| Project | Permit | What the rule says |
|---|---|---|
| Kitchen remodel | Yes | Monona's permit packet lists kitchen remodeling and alterations as needing a building permit, and any electrical or plumbing work needs its own permit too. The city publishes no exemption for cabinet- or countertop-only jobs, so check with the inspector before skipping a permit. Permits: building, electrical, plumbing.(source) |
| Bathroom remodel | Yes | Bathroom remodels need a building permit. Any plumbing, electrical or ventilation work needs its own permit, and the city publishes no exemption for swapping fixtures in place. Permits: building, electrical, plumbing, HVAC.(source) |
| Finish a basement | Yes | Finishing an unfinished basement needs a building permit, plus electrical, plumbing and HVAC permits for that work. Permits: building, electrical, plumbing, HVAC.(source) |
| Remove or move a wall | Yes | Monona requires a permit for all remodeling and alterations, including interior changes, so removing or moving walls needs one. The city doesn't publish separate rules for load-bearing and non-load-bearing walls. Permits: building.(source) |
| Build or replace a deck | Yes | New decks need a building permit, and the city publishes no size or height exemption. The Building Inspection page points deck builders to the state UDC deck guide (Appendix B commentary). The stormwater form attached to the permit application treats decks as impervious surface unless the owner proves otherwise, so you have to report the deck's area. Permits: building.(source) |
| Replace deck boards or railings | Ask | Monona's web pages and permit packet don't say whether replacing deck boards or railings in kind needs a permit. The building code (Chapter 175 on ecode360) was blocked by a bot check, so it couldn't be checked. |
| Replace windows, same size | Yes | Replacing windows needs a building permit. The city's list doesn't separate same-size replacements from other window work. Permits: building.(source) |
| New or larger window (egress) | Yes | Cutting a new or larger window opening changes the exterior and the structure, and Monona requires a building permit for any change to the exterior and any alteration. Even plain window replacement needs a permit. Permits: building.(source) |
| Replace exterior doors | Ask | Exterior door replacement isn't on Monona's permit list. The general rule covers 'any additions and/or changes to the exterior,' so ask the inspector. The code on ecode360 couldn't be checked. |
| Re-roof | Yes | Re-roofing needs a building permit. The city doesn't separate tear-off from overlay or say anything about replacing sheathing. Permits: building.(source) |
| Replace siding | Yes | Re-siding needs a building permit. Permits: building.(source) |
| New flooring | Ask | Flooring isn't on Monona's permit list, and the city doesn't say it's exempt. The general rule covers 'any additions or changes to the interior,' so ask the inspector. The code on ecode360 couldn't be checked. |
| Replace a water heater | Yes | Replacing a water heater needs a permit. Monona names it, along with furnaces, central air and water softeners. Permits: plumbing.(source) |
| Build a fence | Yes | Every fence on a residential lot needs a fence permit, which the Zoning Administrator and Building Inspector review together. Fences can be up to 6 ft in side and rear yards, and can't extend past the front of the house. Street-yard fences must be decorative natural material, at most 42 in tall and 6 in back from the property line. Shore-yard fences can be at most 42 in tall and 10 ft from the ordinary high-water mark. The fee is $100: $50 for zoning review and $50 for the building permit. Permits: zoning, building.(source) |
Checked October 2026 against the City of Monona sources listed below.
Who to Call
City of Monona Building Inspection
Phone: 608-222-2525
Email: bldinspec@ci.monona.wi.us
Permit office website
Inspection is contracted to General Engineering Company. Apply on its online permit portal (the city's preferred route) or email a paper application. Inspections are requested from General Engineering at 608-745-4070.
Permit Fees
Monona doesn't publish a general residential fee schedule online. The inspector calculates fees from your application and plans, and the fence form says fees are set under code § 175-9 (on ecode360, which was blocked). The only published residential fee found is the fence permit: $50 zoning review plus $50 building permit, paid when the permit is issued. Card payments carry a 2.75% user fee.(fee schedule)
Worth Knowing in Monona
- The permit application has a Stormwater Utility form for any project that changes impervious area. Decks count as impervious unless the owner can prove otherwise, so a new deck or addition can change your stormwater utility charge.(source)
- Lakefront lots have shore-yard limits: fences max 42 in tall and at least 10 ft from the ordinary high-water mark, and only boathouses, boat shelters, landings and piers are allowed as accessory structures in the shore yard.(source)
- The city has a separate Erosion Control and Stormwater Management permit application. It asks for new impervious area, total soil disturbance, and whether any digging goes below elevation 847.7 ft.(source)
- A separate zoning permit is required for any construction, substantial relocation or substantial enlargement of a structure.(source)
- The building inspector holds walk-in office hours Monday, Wednesday and Friday, 9 to 10 a.m., at City Hall, or you can call 608-222-2525 for an appointment.(source)
- Work in the city right-of-way (driveway aprons, sidewalks, curb) needs a separate Public Works right-of-way permit. Only the water utility may turn curb stops on or off, with 48 hours' notice.(source)
- The application lists contractor license fields for a Dwelling Contractor Qualifier, Master Electrician, and Plumbing and HVAC contractors. Owners applying for a construction permit sign the state's cautionary statement about hiring uninsured contractors (Wis. Stat. 101.65(1r)).(source)
Other Towns
- City of Madison
- City of Middleton
- City of Fitchburg
- Village of Shorewood Hills
- City of Sun Prairie
- City of Verona
- Village of McFarland
- Village of Maple Bluff
Sources
- mymonona.com/125/Building-Inspection
- mymonona.com/548/Building-Permit-Application
- mymonona.com/DocumentCenter/View/9/Building-Permit-Application
- mymonona.com/1534/Zoning-Code-Permits
- mymonona.com/DocumentCenter/View/15425/Monona-Fence-Permit-Application
- mymonona.com/DocumentCenter/View/15421/Monona-Accessory-Structures-One-Pager
- mymonona.com/DocumentCenter/View/12290/EC_SWM-Permit-Application-Form_Revised-2022
- mymonona.com/264/Applications-Permits